Versova-Bandra Sea Link Gets Approval From Maharashtra Government

The Maharashtra government today accorded administrative approval to the Versova-Bandra sea link (VBSL) project, eight years after the state cabinet committee on Infrastructure (SCCI) cleared it. In a Government Resolution, the state has pegged the project cost to be around Rs 7,502 crore and its length is estimated to be about 17.17 km. The SCCI had cleared the project on August 18, 2009.
Calendar-icon

By PTI

clock-icon

1 mins read

Calendar-icon

Published on December 8, 2017

Follow us on

google-news-icon
Story

Highlights

  • The projct was origianlll y approved in 2009 by SCCI
  • Prevailing toll charges shall apply to the new sea link as wwlll
  • VBSL will have connectors at Bandra Juhu Link Road & Versov

The Maharashtra government today accorded administrative approval to the Versova-Bandra sea link (VBSL) project, eight years after the state cabinet committee on Infrastructure (SCCI) cleared it. In a Government Resolution, the state has pegged the project cost to be around Rs 7,502 crore and its length is estimated to be about 17.17 km. The SCCI had cleared the project on August 18, 2009. However, it took another four years, for the government to get the Coastal Regulation Zone (CRZ) and environment clearance from the Centre which were given in January 2013, an official said.

In extending the area in length, the government has approved the design plan at a height of 900 meters from the coastline, states the GR. The main four by four lane bridge of VBSL will be 9.60 kms. The cable stayed bridge will be 0.30 kms long and the Balance Cantilever Bridge will be 0.10 km long.

Besides this, the VBSL will have connectors at Bandra, Otters Club, Juhu Link Road and Versova Link Road. There will be toll plazas at Bandra, Carter Road, Juhu-Koliwada and at Nana-Nani Park, it added.

The existing prevailing toll rates shall apply to the VBSL and the concession period shall be up to 2052. In case there is any change in the toll tax policy in the future, the concession period will be revived as per the toll tax policy prevailing then, it stated.

The GR states that the Maharashtra State Road Development Corporation (MSRDC) shall appoint two separate contractors for toll collection and repairs and maintenance of VBSL. The government has also approved the MSRDC to set up Special Purpose Vehicle (SPV) to raise loan.